Prepared By Mohammed Imaduddin Asim Rev: 2
ABOVE GROUND PIPING Standards Followed for Material and Construction:
ASTM: American standard of testing & materials.
ASNT: American Society for Non-Destructive Testing.
ASME: mericanSocietyforMechanicalEngineering
AWS:
American Welding Society.
API:
AWWA: American Water Works Association.
ANSI: American National Standard Institute.
AISI: American Iron & Steel Institute.
API . American Petroleum Institute.
NACE: National Association of Corrosion Engineers
Standard for Construction of Piping System.
- ASME B31.1
- ASME B31.2
- ASME B31.3
- ASME B31.4
- ASME B31.5
- ASME B31.8
- ASME B31.9
- ASME B31.11
- – Power piping.
- – Fuel Gas Piping.
- – Process piping.
- – Pipeline Transportation system for liquid hydrocarbon & other liquid.
- – Refrigeration Piping.
- – Gas transmission & distribution piping system.
- – Building services piping.
- – Slurry transportation piping system.
Construction of Equipments.
- ASME section I: – Rules for construction of power boiler.
- ASME Section II: – Materials. Part A – Ferrous materials.
Part B – Non-Ferrous materials.
Part C – Specification for electrodes & filler wire. Part D – Properties. - ASME Section IV: – Rules for construction of Heating Boiler.
- ASME Section V: – Non- destructive Examination.
- ASME Section VI: – Recommended rules for care & operation of heating boiler.
- ASME Section VII: – Recommended guidelines for care of power boiler.
- ASME Section VIII: – Rules for construction of pressure vessels. (Division I & II)
- ASME Section IX: – Welding & brazing qualification.
- SATIP –
- SAIC –
- SATR –
- SAES –
- SAEP –
- SAMSS –
- RFI –
- PQP –
- SMYS –
- MQMR –
- QMIS –
Saudi Aramco Typical Inspection Plan
Saudi Aramco Inspection Check List
Saudi Aramco Test Report
Saudi Aramco Engineering Standard.
Saudi Aramco Engineering Procedure.
Saudi Aramco Materials System Specification. Request for Inspection.
Project Quality Plan
Specified Minimum Yield Strength. Monthly Quality Management Report. Quality Management Information System.
Any Change Or Addition please inform pg. 1 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
PMCC – NCR – P&ID – ISO – UT –
RT –
PT or DPT or LPT– MPT –
PWHT – PMI – HT –
Partial Mechanical Completion Certificate. Non-Conformance Report.
Piping and Instrumentation Diagram. Isometric Drawings.
Ultrasonic Testing is used for (Flaw detection/Evaluation, Dimensional check, Material Characterization ASTM E164-13 welding, E2375 Wrought products, E213 Pipe. Radiographic Testing (Used to find the defects in the welding rays).
Dye/ Liquide/Penetrant Test method used to locate surface-breaking defects. Magnetic Particle Test used for detecting surface and slightly subsurface Discontinuities in ferromagnetic materials.
Post Weld Heat Treatment SAES-W-011.
Positive Material Identification.
Hardness Test. (Tensile Test, Brinell Test, Impact Test).
Tensile Test: Sample is subjected to control tension until it breaks ASTM E8.
Brinell Test: Sample is penetrated with loaded indenter ASTM E10, HB = Test Force F / Surface area indentation A. Impact or Charpy V-notch test: The amount of energy absorbed by a material during fracture ASTM E23 Rockwell Test: ASTM E18-07 same as Brinell test.
PQR – WPS –
SAES-A-004: SAES-A-007: SAES-L-105: SAES-L-108: SAES-L-109: SAES-L-110: SAES-L-150: SAES-L-310: SAES-L-350: SAES-L-410: SAES-L-450: SAES-H-200: SAEP-351: SAEP-379: SAEP-380: SAEP-381: SAEP-388: SAPE-1151: SAEP-1160:
Procedure Qualification Record. Welding procedure specification.
General Requirments for Hydro testing.
Hydro Testing Fluids & Lay-Up procedures.
Selection of Pipes.
Selection of Valves. API-598: Testing & Leakage Test of Valve. Selection of Flanges, Bolts & Gaskets.
Threaded Joints & Branch Connections.
Pressure Testing for Plant Piping / Pipe Lines.
Design of Plant Piping.
Construction of Plant Piping.
Design of pipe lines.
Construction of On-land & Near-shore pipe lines.
Handling & Storage of Pipes.
Bolt Torqueing Procedure.
Quality Issues Notification.
Equipment Deficiency Report.
Escalation Process for NCR.
Cleaning of Piping.
Inspection Requirments for Procurement materials & Equipment. Hydro Test Package preparation procedure.
P&ID: Piping & Instrumentation Drawings used for
1) Line Number 2) Flow Direction 3) Line Limits 4) Equipment’s & Valves 5) Instrumentation.
Isometric Drawings: Isometric drawings will be at 30° degree & detailed drawings for piping which says.
1) Line Number 2) Material details 3) Material Grade 4) Bolts & Gasket Details 5) Joint Number 6) Support Details 7) Component Details 8) Design Pressure 9) Design Temperature
10) IFC Stamp.
How to read Line class numbers: As per SAES-L-105 Para 7-9.
1CA2PXXX=Service
Service
Corrosion Allowance Line Material
Any Change Or Addition please inform pg. 2 imad8asim@gmail.com +966540406799
Pressure Ratings
Prepared By Mohammed Imaduddin Asim Rev: 2
Pressure Ratings: #150, #300, #600, #900, #1500, #2500.
Corrosion Allowance: 0 = 0mm, 1 = 1.6mm, 2 = 3.2mm, 3 = 4.8mm, 4 = 6.4mm, 9 = SAES-L-033. Service: A=Acid, C=Caustic, D=Drain/Swerve, H=Hydrogen, P=Process, U=Utility, W=Water, A=Air
C=Chemical, CA=Caustic, CWR=Cooling Water Return, CWS=Cooling Water Supply For more refer to SAES-L-105 para 9
Material Selection
Pipe
ASME:B36.10 = CS Pipes Selection ASME:B36.19 = SS Pipe Selection
Butt welded fittings
ASME B16.9 = Steel butt welding fittings
ASME B16.28 = Short radius elbows
Socket & Threaded fittings
ASME B16.11 : – Forged steel socket Welding & threaded fittings
Flanges
ASME B16.1 = Cast iron pipes flanges & flanged fittings
ASME B16.5 = Flanged fittings. (Up to 24”) ASME B16.47 = Flanged fittings (Up to 24”)
Valves
ASME B16.10 = Dimension of valves ASME B16.34 = Connection Valves
Pipe CS SS Alloy LTCS
Material
ASTM : A53 Grade A/B, A106 Gr.A/B/C; A333 Gr A/B ASTM : A312 TP 304/304L; A312 TP 316/316L
ASTM : A335 Gr.P1/P2/P5/P7/P9/P11
ASTM : A333 Gr 6 / API 5L Gr X65 & above / ASTM A671 CC 65
Wrought Fittings (Elbows) : Make by bending the Pipe
CS ASTM A234Gr.WP B/C
SS ASTM A403 WP304/WP304L; A403 WP 316/316L Alloy ASTM A234 WP1/WP5/WP7/WP9/P11
LTCS ASTM 420 WPL6
Cast Fittings : Pouring of Molten metal & making shape CS ASTM A216 B/C, A352 LCB/C.
SS ASTM A217 CA15; A296 CA15
Alloy ASTM A217 WC1/WC5/WC6/WC9
Forged Fittings : Make be Hammering & Other process
ASTM A105: ASTM A181.
CS
SS ASTM A182F6 F304/F304L / F316/F316L Alloy ASTM A182F1/F2/F5/F7/F9
LTCS ASTM A350 LF2
Gasket
ASME B16.20 = Metallic Gasket
ASME B16.21 = Nonmetallic gasket
Pipe = Hallow shape use for transmission of fluids/liquids/gases/ from one end to other end. Gr. = Grade
TP = Tubular Product
WP = Weld able Cast.
N = Normalization (Type of Heat Treatment). CS = Carbon Steel
SS = Stainless Steel
Pipe = 3 Types
1. ERW Pipe (Electric Resistance Weld) (Above 85% Efficiency). 2. Seamless Pipe (Above 90 % Efficiency).
3. Spiral Pipe (Above 70 % Efficiency).
Carbon content in: CS
- ASTM Gr. A– 0.25 %
- ASTM Gr. B– 0.30 % ASTMGr.C–0.35%.
Carbon content in: SS
1.ASTM304-0.08% 2. ASTM 304L- 0.035% 3.ASTM316-0.08% 4. ASTM 316L- 0.035%
Any Change Or Addition please inform pg. 3 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Testing: 1) Pneumatic Test 2) Hydro Test 3) Service Test & Others.
- 1) Pneumatic Test: Using Air or other approved gas testing is done.
- 2) Hydro Test: Using Water or Other approved fluids.
- 3) Service Test: Done using same service used in the pipe system.
Pressure Relief valve set for Hydro Test
- 1) Pressure Relief valve 5% below 85% SMYS (Specified Minimum Yield Strength) of material. Example: 100 Psi is the test pressure PSV should be at 105 Psi.
- 2) Pressure Relief valve 10% above 85% SMYS (Specified Minimum Yield Strength) of material.
.
Example: 100 Psi is the test pressure PSV should be at 110 Psi.
3) 7 Days Calibration.
Manifold Design Pressure Rating/Details as per G.I.-0002.102 Para 5
- 1) Manifold Calibration 6 Months.
- 2) 1.2 times the test pressure.
- 3) 100% NDT has to be done.
- 4) Bleed Valve has be provided form over pressuring of system.
- 5) Check Valve has to be provided.
Pressure gauges SAES-A-004
- 1) The calibration one (1) month with next calibration date.
- 2) All gauges shall have 30 to 80% of the full range. (Pressure B/W 30-80 %).
- 3) Min 2 Gauges in system 1 in system 2nd at Manifold. 5% variation in 2 gauges.
- 4) Additional gauges can be installed for big systems
Vents and Drains
- 1) Vent at high point & Drain at low point.
- 2) Vents and drains used only for the pressure test shall be Plugged & seal welded and penetrant tested.
Temporary Connections and Supports.
- 1) Temporary supports shall be installed prior to hydrostatic testing.
- 2) All temporary items installed for testing (e.g., manifolds, valves,
- 3) Blinds, spacers, supports) as per SAES-A-004 Para 10.
SAES-A-007: Hydrostatic Testing Fluids and Lay-Up Procedures.
Water Quality for Hydro Test.
CALCULATIONS.
TEST BLIND CALCULATION
- 1) To maintain water quality oxygen scavengers are used, to calculate follow SAES-A-007 Appendix-1 Page 19.
- 2) Carbon steel / Alloy Steel 14 days water in system, residual concentration greater than 20ppm and oxygen concentration less than 10 ppb (Hydro Test)
- 3) Stainless Steel Equipment for 300/400 Series of chloride content is 50ppm to avoid pitting & stress corrosion cracking.
- 4) Contact of water with SS is not more than 4 days.
Lay-Up or Preservation of System:
1) Wet Lay-Up 2) Dry Lay-Up 3) Inert Gas Lay-Up 4) Ambient Lay-Up 5) Other Lay-Up.
All piping and equipment shall comply with the lay-up procedures per SAES-A-007. Wet-Lay Up: Can be achieved by using
- Water of 10 ppb to 20 ppm shall be maintained with scavengers.
- Close the system with air tight and check pp values for every 6 moths till the system used. Dry Lay-Up: Can be achieved by using 1) Hot Air 2) Inert Gas (dew Point) 3) Drying Chemicals.
- Darin the water completely
- Used the scrappers to remove the water from pipelines
- Blow the Dry-Air using Oil free compressor not more than 12 Hr.
- Check the Dew Point at -1 Degree, if using Sweet gas (Inert Gas or Nitrogen) pressure
- The system at 30 Psi. (Para 5.2.3.7) if pressure is less than adjust. Inert Gas Lay-Up: Using Argon or Nitrogen gas
- Darin water from hydro-test using scrappers.
- Remove the water from system using inert gas or Nitrogen till no water comes out & shut
- Down the system till start-up at 30 Psi.
SAES-A-004: General Requirements for Pressure Testing
Any Change Or Addition please inform pg. 4 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Ambient Lay-Up: System shall meet following requirements.
- Drains at low points
- Corrosion allowance
- Pitting can be tolerate
- Particulate rust can be tolerate. Other Lay-Up:
Shall be approved from CSD (Consultant Service Department) and Owners representatives. SAES-L-105: Piping Material Specifications.
Material Specification for Pipes / Fittings / Valve for more details refer SAES-L-105
01-SAMSS-035 = API Pipes 01-SAMSS-332 = Grade B Pipes 01-SAMSS-333 = Grade C Pipes
02-SAMSS-001 = low Tem. Service Fittings 02-SAMSS-005 = Butt Weld Fittings 02-SAMSS-011 = Flanges
04-SAMSS-001 = Gate Valve 04-SAMSS-003 = Low Temp Valve 04-SAMSS-005 = Check Valve
SAES-L-108: Selection of Valves. i.) Service ii) O&M requirments iii)
04-SAMSS-048: Valve Inspection & Testing Requirements. Field Testing as per para 4.7:
SATIP: Valve Inspection, Testing
SAIC-L-2024: Inspection of valves
- Testing location shall be specified.
- Valves shall be subjected to a high pressure hydrostatic seat test prior to installation in the line.
- Pressure/Duration/Leakage and acceptance criteria as per manufacturer.
- No leakage in Isolation valves. Same Valve Body Parts:
i) Body 2) Bonnet 3) Seat 4) Spindle 5) Stem 6) Packing 7) Wheel Handle 8) Actuators 9) O-rings ETC., Valves: Valves are used to control the flow in the process whenever is required and selection of valve Depends on Services, Pressure & Ratings.
Valve Ratings & Class: Valve Connections: Valve Material:
150#, 300#, 600#, 900#, 1500#.
1) Bolted 2) Welded 3) Threaded (Rare).
1) Cast Iron 2) Steel 3) Stain less Steel 4) Alloy.
(A & M):
(MOV): Manual: Automatic: Actuators:
Automatic & Manual.
Motorized operated Valve.
It’s done Manual
It’s controlled with actuators (Actuator will have motor in it).
This is an instrument which will be connected to SCADA and valve will be controlled From DCS room. It’s mainly used to control the flow and pressure in the system
Types of Valves & Functions. Butterfly Valve:
Control Valve:
Gate Valve:
Ball Valve:
1. Disc or Plate is used to regulate or prevent the flow.
2. Disc or Plate present in the flow. Consider the pressure drop. 3. This Valve is Manual or Motorized.
1. Rotatory Motion & Linear motion to control the flow.
2. This Valve is motorized. (Actuators & Motors are used)(MOV).
3. Used to Control the flow as a result control in liquid level, pressure & temp.
1. Seat (Plate) is moved up & down to control the flow. 2. It seals the surface between Gate and Seat. (A & M). 3. it’s often used in liquid services.
1. Ball with hole is used to control the flow.
2. When hole is lined the flow is passed and it rotates at 90 Degree
Any Change Or Addition please inform pg. 5 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Plug Valve:
Globe Valve:
Check Valve:
API-598:Testing of Valves
1. Plug rotate in the body of Valve to control the flow.
2. Plug valves have one or more hollow passageways going sideways through
The plug, so that fluid can flow through the plug when the valve is open.
1. Disc is used to control the flow.
2. Valve used for regulating flow in a pipeline, consisting of a movable
Disk-type element and a stationary ring seat in a generally spherical body.
1. Swing, Disc & Ball are used to control the flow.
2. It allows to flow fluid in one direction.
3. The pressure of forward fluid flow opens the valve (Swing, disc or ball) and the
pressure from backflow closes it, forcing the (Swing, Disc or Ball) against seat.
i. ii. iii. iv.
Testing depends upon Ratings of Valve (150#, 300#, 600#, 900#, and 1200#).
Types of Testing
1) Seat Test (30Sec – 2Min) Max can be done by
i) Pneumatic Test ii) Hydro Test
Seat Test will be carried out by two methods and done as per Data Sheet & Vendor. During testing we have to check the leakage from Packing & Seat.
2) Shell Test (30Sec – 2 Min) Max
1. Hydro Test
Seat test shall be carried out for (30Sec – 2 Mint).
During testing we have to check the leakage.
During testing we have to check Bubble & Count the bubble.
SAES-L-109: Selection of Flanges, Stud Bolts and Gaskets:
Type of Flanges as per para 6
i) Weld Neck (WN) ii) Threaded iii) Socket Weld iv) Slip On v) Lap-Joint vi) Blind vii) Orifice viii) Isolating. Face of Flanges as per para 6
i) Raised Face (RF) ii) Ring Joint (RJ) iii) Flat Face (FF).
Blinds:
- 1) All blinds hydro test shall meet the requirements of ASME B31.3, paragraph 304.5.3.
- 2) Standard Drawings for blinds SAES-L-109 para 10.
Note: Selection of flanges depends on
End connection (Bolted, Weld Neck and Slip-On) Ratings
Operation & maintenance of system.
Service & temperature.
Gaskets:
i) Spiral Wound Metallic ii) Metallic iii) Non-Metallic
PIKOTEC gasket is used in dis-similar materials or other approved gaskets.
Note: Selection of gasket depends on
1. Flange face. (Raised Face, Flat Face) 2. Ratings.
3. Temperature.
4. Services.
Bolts & Nuts as per SAES-L-109 para 12 and ASME.
- ASTM A193 Grade7: Bolts
- ASTM A320 Grade3: Bolts
- ASTM A194 Grade 2H: Nuts
- ASTM A194 Grade 4 or 7: Nuts
Any Change Or Addition please inform pg. 6 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
SAES-L-110: Threaded Joints, Branch Connections.
Socket Weld requirements: SAES-L-110
- 1) For hazardous services 1 1⁄2” to 2” Max
- 2) For Sour services 1”
- 3) 1.5mm to 3 mm gap has to maintain before welding.
Threaded Joints: SAES-L-110
- 1) For hazardous services 1 1⁄2” to 2” Max.
- 2) For non-hazardous services 3” Max for 4” required special permission.
- 3) PTFE Teflon tape shall not use above 204°C
- 4) Engagement of Threads as below as per SAES-L-110 para 7.
ND/ Size
Threads
1/2″ – 3/4″ 6 1″ – 1 1⁄2” 7
2″ – 3″ 8 4″ 10
Branch Connection as per SAES-L-110 para 12 shall be made. And as per ASME B31.3 304.
SAES-L-150: Pressure Testing for Plant Piping and Pipe Lines. As per para 7 & 8
- Test shall be conducted 1.5 times the design pressure.
- All Joints shall be exposed for visual leakage.
- No painting shall be done on weld joints.
- System shall be pressurized for 30 minutes at 100% & pressure has be
- Increased as 30%, 60% and 100%.
- All punch A items shall be cleared. Test Preparation
- New piping systems shall be cleaned in accordance with SAES-L-350.
- Soft Seated Valves & Control Valves shall be removed. Flushing.
- Flushing of piping as per SAES-L-150.
- Remove temporary supports after flushing & Draining of system. Water Flushing.
- All CS piping systems shall be flushed using high pressure [60.8 mPa (8.8 ksi) minimum] As per SAES-L-350.
- Stainless steel lines chloride content shall be less than 50 mg/L with dew point -1°C. SAES-L-350: Construction of Plant Piping.
- All material shall have clear marking.
- All material shall be procured form approved Vendor.
- Fit-Up & Tolerance as per SAES-L-350 para 9.
- Shop fabrication of piping shall be in accordance with 01-SAMSS-010. Erection and Installation refer SAES-L-350 Para 15
1. Internal Cleaning of Pipe. 2. Visual Inspection for Damage. 3. Using Nylon Ropes. 4. Tag/Spool as per
drawing/Elevation. 4. Spool shall not directly placed on Ground.
Flange Alignment as per SAES-L-350 Para 9
- Vertical bolt hole offset: ± 2.4 mm
- Horizontal bolt hole offset: ± 2.4 mm
- Rotational offset: ± 2.4 mm.
- Flange face tilt across diameter: 0.025mm per 25 mm (0.001 inch per inch)
- Maximum of 0.672 mm (0.030 inch).
- Flange face separation, gasket thickness: ± 1.6 mm.
- Combination of vertical, horizontal and rotational offset: ± 3.2 mm.
Any Change Or Addition please inform pg. 7 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
SAES-H-200: Handling & Storage of Coated Pipes.
Handling of Material:
- All painted & Non Painted materials shall not be placed directly on ground. (150 mm above ground).
- Pipes shall place on mounts or sleepers (SAES-L-350)
- Bevel End, Bends, Pipe wall & Coating shall be protected.
- Slings or Nylon ropes shall be used from loading & Off-Loading.
- No steel metal shall be used.
- Coated pipes shall not be dragged or pulled.
- Fittings and valves shall be stored in shipping crates or on racks. Stacking & Storage of Materials:
150 mm above the ground all material shall be placed.
Material shall be placed level to avoid dropping or Slipping using pads or skids. Cover all the material from foreign material using polyethylene or equivalent. Stacking height shall not exceed 1.5 Meters.
Repair of Coated Material as per SAES-H-200 para 6 and Holiday test has to be conducted. SAEP-351: Bolted Flange Joints Assembly or Bolt Torqueing.
- Types of Bolt Torqueing 1) Manual. 2) Hydraulic. (Refer Method Statement).
- Tools shall be calibrated with 6 months validity.
- Bolts tightened in accordance with SAEP-351.
- Bolt Torqueing Valves as per SAEP-351-02 table for all gaskets except insulating gasket
- Bolt Torqueing Valves as per SAEP-351-03 table for isolating gasket.
- Bolt Torqueing sequence as per SAEP-351 Table 1 for 4 to 32 bolts.
- Bolt Torqueing sequence as per SAEP-351 Table 2 for 36 to 68 bolts.
- Bolt Torqueing as 30%, 60% and 100% with star pattern.
- Bolt Torqueing at 100% circumferential.
- Thread shall be visual as per SAEP-351 after bolt torqueing. Tightening Procedure where Leaks Occur During Pressure Testing.
- Inspect stud bolts and nuts for defects or damage to threads or improper cleaning of threads.
- Inspect flange faces for damage, misalignment.
- Inspect gasket for damage or defects.
- All completing the inspection torque again. SAEP-379: Quality Issues Notification. Says refer to SAEP-381. SAEP-380: Equipment Deficiency Report (EDR).
Inspectable Material by VID (Vendor Inspection Department) categories defined below.
1) Category A 2) Category B 3) Category C 4) Category B.
1) Category A: Material procured under this category required visual inspection & released for shipment by VID.
2) Category B: Material procured under this category required review of certificates & released for shipment by VID. 3) Category C: Material procured under this category required no inspection & released for shipment by VID.
4) Category S: Material procured under this category required visual inspection & Inspection & released for shipment by VID
SAEP-381: Escalation Process.
It says about changing of log-Book to NCR from NCR to Worksheet and from Worksheet to Delinquent Worksheet.
Types of Violation. Any violation against Standards/Codes/Procedures/Drawings then (By Client) 1) Minor 2) Moderate 3) Major
1) Minor = log-Book 2) Moderate = NCR (Non Conformance report) 3) Major = Work sheet. Reply to LBE/NCR/WS = i) Root Cause ii) Corrective Action iii) Preventive Action
iv) ACD (Agreed Closing Date).
Any Change Or Addition please inform pg. 8 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
- Response to LBE/NCR within 48 hr.
- Repeated violation with 6 months LBE = NCR / NCR = DWS1 / DWS1 = DWS2 / DW2 = DWS3
- ACD can be extend once, ACD (Change) to = ACD 1.
- If ADC1 is not closed then escalate from LBE=NCR / NCR=DWS1 / DWS1=DWS2 / DWS2=DWS3. Escalation Stages.
- LBE 5 Stages = LBE = NCR = DWS1 = DWS2 = DWS3.
- NCR 4 Stages = NCR = DWS1 = DWS2 = DWS3.
- WS 3 Stages = DWS1 = DWS2 = DWS3.
INCR (Internal Non-Conformance Report). Raised by Contractor or Sub-Contractor.
- INCR is raised within 48 Hr. client has to be notified.
- ACD can be extend once, ACD (Change) to = ACD 1.
- If ADC1 is not closed then escalate from ACD1 (Changes to) = NCR (Client)
- INCR escalate to NCR of client after ACD1. SAEP-1150: Inspection Coverage on Projects.
- Inspection Coverage is covered by,
- PQP = Project Quality Plan (That describes the activities,
- QA = Quality Assurance (Assurance of work from Standards/Code/Specification that will be Implemented at different stages of project execution.
- QC = Quality Control (Execution of work as per Standards/Codes/Specification & quality will be Maintained by Inspection & Testing.
- Organization Chart = which says about the Quality personal & communication process.
- PQAM/PQCM = Project Quality Assurance Manager/Project Quality Control Manager will be assigned.
- QCL/QCS = Quality Control Lead’s/Quality Control Supervisors as assigned.
- PID = Project Inspection Department (Will be assign to witness/monitor the project execution With level of Insp at different phases).
- QA/QC Inspectors = To assure the quality of work at every activities by testing & inspecting the work And recorded with RFI (Request for Inspection).
- VID (Vendor Inspection Department): Assigned for Material & Procurement.
- Inspection Coverage is done by:
1) ITP (Inspection Test Plan) 2) RFI (Request for Inspection) 3) Level of Inspection. ITP (Inspection Test Plan):
- 1) Which says about the activity for which inspection is required.
- 2) Client/Contractor/Subcontractor involvement during inspection (H/W/S/A/R).
- 3) Procedure/Specifications/Codes required for the activity.
- 4) Inspection Checklist & Inspection Report required for activity.
RFI (Request for inspection):
- 1) Has to be raised as per activity in the ITP.
- 2) Numbering /Assigned QC as per the area/activity.
Level of Inspection (During Construction).
- 1) Hold = Inspection activity has to be witnessed by Client Inspector (PID).(Mandatory)
- 2) Witness = PID witness is required/not required, can be done by Contractor/Sub-Con.
- 3) Surveillance = PID/Contractor QC witness is not required. (Optional)
- 4) Review = Review of documents by PID work cannot be proceed.
- 5) Approval = Documents required for approval form PID work cannot be proceed.
QA/QC Coverage: Quality department provides inspection services in various phases of the project By direct inspection, monitoring and quality assessments.
Weekly Project Progress & QC Meetings: Discuses the look-ahead plan, quality issues & solve the issues. Weekly Look-ahead plan schedule: Look-ahead plane is a planning to cover the work activity and special
Importance to any new activity.
(Engineering, Procurement & Construction) necessary to achieve quality in the delivery of
standards, responsibilities, processes
a project).
Any Change Or Addition please inform pg. 9 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
SAEP-1151: Inspection requirments for contractor procured materials & equipment.
- Level of inspection for VID, PID, SAID.
- Level 0/1/2/3/4 = applicable for material & equipments at manufacturer.
- Level A/R/S/W/H/ITP = applicable inspections for construction.
AS per SAEP 1151 level of inspection for Material & Equipment
AS per ITP level of Inspection for Construction
Approve (Documents will be submitted for Approval)
Review (Documents will be submitted for Approval)
Surveillance (Work can be proceed)
Witness (Work can be proceed with permission)
Level 0 Level 1
Level 2 Level 3 Level 4
Documents required, No Vendor inspection A
Final Inspection prior to Shipment. R
All Inspections, Hold/Witness/Surveillance S before Shipment.
Inspection Daily/Weekly/Bi-Weekly basis. W
Resident Inspector continuously monitoring the work.
H Hold (Work cannot be proceed without presence of PID/Inspector)
SAEP-1160: Tracking & Reporting of Welding, NDT & Test Package preparation. Contents of Package.
- Test Flow Diagram.
- P & ID Marked.
- Isometric Marked.
- Test Limits.
- Water Analysis Report.
- Weld Joint Summary.
- NDT reports.
- Calibration Certificates of all components.
- Manifold Diagram and Calibration report.
- Pre-pressure test Check List (Punch List).
- Reinstatement report.
- Temporary blinds & Components & supports Identification.
- Bolt Torqueing Report.
- Safety Sheet.
- Lay-Up method (If required). SCHEDULE Q
1. General 2. Quality Management System Requirments (QMSR). 3. Documents Requirments. 4. Management Responsibility
5. Resource Management 6. Project Realization/Execution.
7. Measurements/Analysis/improvement.
Attachment i: Contractor & Sub-Con personal Qualification.
Attachment ii: Company Standards & Procedures containing quality requirments. Attachment iii: Quality requirments for material.
Attachment IV: Quality requirments for construction phase.
Attachment v: Quality system deliverables.
1. General: Minimum quality requirements for Contractor – Sub-Con. PQP/ITP/Personal Qualification = for review & approval.
30 Calendar days
Any Change Or Addition please inform pg. 10 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
- QMSR: Implementation of ISO: 9001 latest version 21 days for approval.
- Documents Requirments: Documents req. for construction, QP/ITP/SATR .
- Management Responsibilities: Internal Audit recommended action.
- Resources Managements: 1. All quality personnel for project. 2. Mobilization & De-mobilization date of Quality personnel. 3. Assign – Re placement – Change – Leave – Vocation of Quality personnel.
- Project Realization/execution: 1. Design 2. Procurement 3. Construction 4. Pre-Commissioning.
- Measurements/Analysis/Improvement:
1. NCR and LBE shall be reply within 48Hr raised by Owner.
every 6 months and within 2 weeks
7 days for approval for a revision
Attachment i:
- Summary of Open/Close NCR/LBE with dates shall be maintained.
- Contractor Internal (INCR) shall be reported .
- Investigate Root-Cause and initiate corrective action .
- Internal Audit shall be carried out 6 Months.
- Full Audit shall be done (or as per Quality plan).
- Audit reports shall be submitted within with corrective action.
Contractor & Sub-Con personnel qualification.
1. QCS = shall have Degree & 8 years Exp. Or Diploma & 10 Years Exp. 2. QC = shall have Degree & 5 years Exp. Or Diploma & 7 years Exp.
3. Quality personnel requirments.
Attachment iv: Quality requirments for construction phase.
- RFI = 24Hr at site & RFI = 48Hr for week end & remote areas. 1 week = Holiday.
- SATIP/SAIC/SAIR = shall be used as per the activity.
- 2 week look-ahead schedule of all planned quality activities shall be submitted.
- Implementation of special process. (Qualification of Technicians).
within 48Hr
(Stages) 15% & 60%
within 7 day
14 days
All procedures & Qualification shall be submitted for Review/Approval
.
21 day’s prior to start of work
Special Process for Mechanical
Work Procedure Qualification A = Approval Req
R = Review Req
Personnel Procedure Qualification Approval Req = Yes/No
Personnel Qualification Approval Req = Yes/No
Welding/Brazing A NDT A PMI A
HT A Pressure testing A Valve Test A Coating & Lining A Gasket & Bolt torquing A Hot taps & Tie inns A HVAC testing A RTR pipe works A
Yes Yes No No No No No No No No No
Yes Yes Yes No No No Yes No No No Yes
5.
6.
Position
QA Manager QC Manager
Piping Inspector Valves Testing
Maintain calibration certificate log status with expiry dates. Quality personnel requirments for Project.
Contractor
One (1) Full Time One (1) Full Time
One (1) Full Time for (5) Sub- Con Inspector
One (1) Full Time
Sub-Contractor
N/A
One (1) Full Time
QCS (Supervisor) | One (1) full time per discipline for each eight (8) inspectors | One (1) full time per discipline for each eight (8) inspectors |
One (1) Full Time for (15) workers
One (1) Full Time
Any Change Or Addition please inform pg. 11 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Quality System Deliverables: | ||
Title First Submittal to COMPANY Subsequent submittals to COMPANY | ||
Quality Plan: Paragraph 3.2 of Schedule “Q” Twenty one (21) calendar days after the effective Within 7 calendar days of each date of Contract and for any significant changes revision requirement | ||
Organization Chart(s) Paragraph 5.12 of Schedule “Q” With Quality Plan submittal When changes occur | ||
Personnel Qualifications: Paragraph 5.6 of Schedule “Q” Prior to assignment of personnel on the project Prior to bringing new Quality personnel on the project | ||
Quality Audit Schedule: Paragraph 7.3.2 of Schedule “Q” Within twenty one (21) calendar days of the Within 7 calendar days of effective date of the Contract revisions | ||
Audit Report: Paragraph 7.3.5 of Schedule “Q” Within fourteen (14) calendar days of completion of the audit and re-audit. | ||
CONTRACTOR, Vendor and Subcontractor non-conformities: Paragraph 7.5.3 of Schedule “Q” | Within forty eight (48) hours of reporting each nonconformance | Notification of clearance required |
Non-conformance Summary: Paragraph 7.5.5 of Schedule “Q” After the first nonconformance is issued Weekly for the Project Progress Meeting | ||
Two-week look-ahead schedule; Paragraph 3.3 of Attachment II! Paragraph -1.6 of Attachment IV- | Fourteen (14) calendar days before the start of any inspection activity of first purchase order or start of construction activities | Weekly |
Special Process Procedures and Personnel Qualification Procedures: Paragraph 3.11 and 3.13 of Attachment Ill; Paragraph 2.1 of Attachment IV | Twenty one (21) calendar days prior to operation or test | Prior to execution |
Construction Inspection and Test Plans: Paragraph 1.1 of Attachment IV | One month prior to start of construction WORK | Revision -Approval prior to execution |
Hydrostatic Test Package: Paragraph 2.1, Attachment IV. Prior to each hydrostatic test. Prior to each hydrostatic test. | ||
Any Change Or Addition please inform pg. 12 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
General Points:
- Types of Joint 1) Butt Joint 2) Threaded Joint 3) Bolted Joint 4) Socket Joint.
- Type of Gasket 1) Metallic 2) Non-Metallic 3) Pikotek Gasket used between dissimilar material (CS-SS)
- Types of reducers 1) Concentric 2) Eccentric reducers.
- TypesofElbow 1)90° 2)45°
- Spectacle Blind = Have two blinds one open & one close, the purpose of this blinds is for maintenance of
Supports:
- Shoe Support.
- Saddle Support.
- Leg Support.
- Dummy Support (Trunnion Supports).
- Anchor Support
- Cantilever Support.
- Guide Support.
- Spring Support.
- Hanger Support.
- Special Support. Long Radius Elbow: 90
Line without closing full line. Or used as Isolation of line.
LRE 90° Elbow SRE 90° Elbow
= 1.5 X Dia of Elbow in Inches X 25.4 = 1.5 X 10” X 25.4
= 381 MM.
= 1 X Dia of Elbow X 25.4
= 1 X 10 X 25.4 = 254
45° Elbow SRE 45° Elbow
= 15.7 X Dia of Elbow = 15.7 X 10
= 157
= 10.5 X Dia of Elbow = 10.5 X 10
= 157
Note: Take the Length of the elbow and subtract from the total length of the pipe to get actual length of pipe Example: Actual Length of Pipe = Elbow – Total Length of Pipe.
Actual Length of Pipe = 10” 90° Elbow – 2000 MM Pipe. = 381 – 2000.
= 1619 mm.
Ovality: Non-Circularity of a Pipe/Fittings is called Ovality.
104.2
ASME B31.1 – 2001
Curved Segments of Pipe (B) for ferrous material, when the radius of a bend is 5 nominal pipe
diameters or greater, and the nominal wall thickness of the pipe is schedule 40 or thicker, the difference
between maximum and minimum diameters shall not exceed 8% of average measured outside
diameter of the pipe before bending.
Any Change Or Addition please inform pg. 13 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
QA/QC
Difference between QA & QC.
QA = Quality Assurance.
QA = Will assure that the work will be
Executed as per which Standards, Codes & Specification.
To maintain the level of Quality in a Service or Product at different stages.
What is Schedule Q?
QC = Quality Control.
QC = Work should be executed as per Standards,
Codes & Specification by testing & Inspection.
1. Minimum Quality has to maintained by Contractor or Sub-Contractor during execution of work at different Stages.
- Quality Management System Requirments.
- Documents Requirments.
- Management Responsibilities.
- Resource Management.
- Project Execution.
Responsibilities of QC Inspector.
1. Surveillance & Monitor the activities as Site.
2. Work shall be executed as per Standards, Codes & Specification.
3. Work shall be done as Approved ITP / Drawings / IFC drawings (Issued for Construction). 4. Updated drawings shall be used at Site.
5. Raising RFI & Closing RFI.
6. Maintain the documents & reports on daily basis and update the data for tracing.
7. Perform internal inspections before raising RFI.
8. Assure availability of tools & Equipments during inspection.
9. Familiar with Codes & Standards.
10. Inspection of work done by Construction.
11. Witnessing & Monitoring during execution of work.
12. Work shall be carried out with Safety.
13. Tool box meeting & explaining the work to construction to maintain quality.
14. Guide the construction as per the priority of work.
15. Issue NCR to construction whenever required.
Responsibilities of Piping QC Inspector:
- Approved Documents/ITP’s/Procedure used.
- Material Receiving Inspection.
- P.O: Purchase Order
- Delivery Note
- IRN: Inspection Release Note (3rd Party)
- IRC: Inspection Release Check List (3rd Party).
- Color Coding
- MTC: Mill Test Certificate 1)Heat Number 2)Material Specification 4) Mechanical Properties (Tensile Test, Tough/Impact Test for LTCS only). 5) Chemical Properties (ASEM SEC-II part A/B).
- Material Handling and storage. (Refer Above)
- Fabrication & Fit-Up.
- Drawing.
- Material & Color Coding.
- Fit-Up inspection as per WPS
Material Receiving AS PER
SATIP-L-350-01: Material Receiving
SAIC-L-2005: Pipes, SAIC- L-2006: Fittings
SAIC-L-2007: Gasket, SAIC-L-2008: Bolts
SAIC-L-2009: Flanges
.
SHOP FABRICATION AS PER
- Root Gap:
- Root Face:
- High-Low:
- Bevel Angle:
- Heat Tractability on fabricated pipes.
- Orientation of fittings as per drawings.
- Rollings & Size.
3-4 mm.
0.2 mm.
1.5 mm. 37.5 Degree.
SATIP-L-350-08: Shop Fabrication
SAIC-L-2035: Cutting & Fit-Up
Any Change Or Addition please inform pg. 14 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
5. Releasing for Painting/Site.
Once welding is finished mark the joint details on template & release for paint.
- All the weld joints shall be protected from painting.
- Bevels/End of pipes & Fittings shall be protected from paint.
- Installation & Erection.
- Internal Pipe should be clean.
- Elevation of pipe as per drawing to know the location.
- Templates for the joint details.
- Line Check/Pre-Pressure Test/Punch List. Punch A: Testing cannot be procced without clearing Punch A.
- Welding has to be completed.
- Installation of Vents & Drains.
- Installation of Supports.
- Close all the Log Books & NCR related to package.
- Removal of Paint & Masking tape from weld joints.
- Calibration Certificates (Gauges/Manifold/PSV).
- Temporary Blind Installation details.
- Temporary Welding DWR.
- Water Analysis report.
- As Build Drawings shall be approved.
- Bolt Torquing.
- Temporary supports installation where ever is required.
- Orientation of valves. Punch B:
- Paint Touchup.
- Removal of Temporary Items.
- Seal Weld on Vents & Drains.
- Draining of Line.
- Flushing of Line. Punch C:
Pipe Installation AS PER
8. Hydro Test.
Paint Touch Up.
House Keeping.
(Its type of method used to check the leak in the System using water). Package Submission/Review/Approval.
Test Limits identification.
NDT & reports. (Clearance)
Weld Summary. (Clearance)
SIS (Safety Instruction Sheet).
Clearing Punch A.
Hydro Test preparation.
Fill the water in the line.
Calculation for Hydro Test.
SATIP-L-350-01: On-plot Piping Installation
SAIC-L-2011 & L-2012: Installation & Erection
SAIC-L-2017: Internal Cleaning of Line
Design Pressure of Line 100 PSI. (1 Bar = 14.5 Psi) Hydro Test Pressure.
1.5 X Times Design pressure.
100 X 1.5
150 Psi.
Manifold Pressure. (Calibration 6 Months) 1.2 X Times the test Pressure.
150 X 1.2
180 Psi.
Pressure safety Valve. (Calibration 7 Days)
0.5 Times the test pressure (or) 10 % of test pressure which one is less? 150 X 0.05 = 7.5 Psi
157.5 Psi.
Or Bleed Valve
PG = Pressure Gauge.
PSV = Pressure Safety Valve.
CV = Check Valve.
TB = Test Blind / Temporary Blind. B = Bolts.
H = Hose/Pipe.
SATR-A-2008: Internal Cleaning of Line
Punch List AS PER
SATIP-A-004-02: Hydro test of On-plot Piping
SAIC-A-2010: Pre-Test Punch List
SATR-A-2007: Punch List
Any Change Or Addition please inform pg. 15 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Pressure Gauge. (Calibration 6 Months).
Pressure should be between 30 to 80 % in the dial range.
Pressure the line by 30%, 60% & 100%
Hydro Test pressure 150 Psi (Pressure shall be increased gradually).
.
- Hydro Test complete (No leak)
- Darin the line.
- Flush the line.
- Close the line and protect the line. Bolt Torquing: As per SAEP-351 (Torque wrench 6 Months calibration)
30% = 45 Psi hold 10Min 60% = 90 Psi hold 10Min
100% = 150 Psi hold 30 Min
1. Star Pattern 30% Value
60% Value 100% Value
Bolt Torquing is done by two type Manual & Hydraulic. Manual & Hydraulic follow the same method.
2. Circumferential /Circular 100% Value.
Lay-Up: SAES-A-007 Refer the above documents.
Reinstatement:
SAIC-A-2007: Lay-Up Procedure
PMCC:
- Drain, Flushing & Hydro test completes & documents are accepted.
- All Vents & Drains are seal Welded.
- All temporary components shall be removed.
- Clear Puch B & Punch C.
- Jacking Screw, Process blind, Spectacle blind, Spade etc., correctly installed.
- Spring hangers & Components as per Mfg.
- Reinforcement pad Air Test 5 Psi.
- Close weep hole with heavy grease.
- Chain wheel operator installed.
- All instruments & Valves are installed in correct flow.
- Orifice flow elements installed.
- Pressure relief valve installed with calibration tag.
- Gasket / Bolt torquing as to be done.
- All start-up items shall installed (Strainers, Filters Other items restricted from test)
- Lay Up as per Owners approval.
- Chemical Cleaning completed (If required).
- Final line Check as per specification. Partial Mechanical Completion Certificate will be issued to Construction of completion of above activities. Note: Punch B & C or other minor works will be changed to Master Punch that will be given by Pre-Comm & Commissioning team. And will be cleared by them.
Log Book Entry:It’s given when there is any violation in work. (Work Executed against Codes & Standards) NCR: For more refer SAEP-381 Escalation Process.
NCR: Non Conformance report is given for the repeated violation within 6 months.
NCR: Contents.
- 1) Root Cause 2) Corrective Action 3) Preventive Action. 4) ACD (Agreed Closing Date) (Has to be replied within 7 working days).
- 2) ACD (Agreed Closing Date) when we are going to close NCR there is no time limit. If NCR is not closed in ACD we can change the date 1 Time.
Any Change Or Addition please inform pg. 16 imad8asim@gmail.com +966540406799
Hydro Test as per SATIP-A-004-02
SAIC-A-2001: Hydro Test Procedure
SAIC-A-2003: Review of Test Package
SAIC-A-2011: Test Preparation
SATR-A-2009 & SATR-A-2014: Lay-Up Inspection
Pre-Commissioning:
Commissioning:
SAIC-A-2015: Test Pressure Inspection
SATR-A-2001: Pressure Test Report
SAIC-L-2017: Flushing of Line
SATR-A-2008: Flushing of Line Report
SAIC-L-2014: Bolted Flange Inspection
SAIC-A-2006: Reinstatement Procedure
SATR-A-2007 & 2011: Reinstatement (Post-Test) check list
Prepared By Mohammed Imaduddin Asim Rev: 2
SAES-L-070: SAES-L-610: SAES-L-650:
- RTR:
- FRP:
- GRE:
- GRP:
- GRV:
- PVC:
- CPVC:
- HDPE:
Non Metallic Piping & Utility Piping
Installation of Utility Piping. Non-Metallic Piping.
Construction of Non-Metallic Piping.
Reinforced Thermosetting Resin. Fiber Reinforced Plastic.
Glass Reinforced Epoxy.
Glass Reinforced Pipe.
Glass Reinforced Vinyl ester. Polyvinyl Chloride. Chlorinated Polyvinyl Chloride. High Density Poly Ethylene.
14. Material Handling & Storage same as Metallic Piping. SAES-S-070 & SAES-H-200.
All material should shall be protected for direct sun light. All Material should keep in building or shade.
Solvents, Chemicals, bounding agents & Cements shall be kept at 26.7°C Max.
- Test Preparation as per Metallic piping. SAEP-1106
- General Requirements for Hydro Testing as per SAES-A-004.
- Pressure Testing for Plant Piping & Pipe Lines SAES-L-150.
- Hydro Test is conducted for 2 Hr. for the joints exposed for visual leakage.
- Hydro Test is conducted for 24 Hr. for the joints backfilled and recorded on Pressure Recorder.
All the activities as same as Metallic Piping.
Construction Activities as per SAES-S-070 Para 8
Qualification of installer. 1) Shall be trained 2) Trail Joint. 3) Approval from Manufacture.
Excavation of Trenches SAES-S-070 Para 9 & SAES-L-650
- O.D + 300 (300 + 300 =600) trench size Minimum.
- Shall have work space for jointing & other activities.
- Trenches shall be protected from land escape.
- 150 mm ground bed shall be done below the pipe.
- Slop of trench less than 15 Degree.
- 2 or more pipes in one trench distance B/W them is 1 M (SAES-L-650 para 7.2). Backfilling of Pipes SAES-S-070
- Clean sand shall be used for backfilling.
- Backfilling shall be conducted layer by layer as 300mm.
- Compaction has to be done (Manually) with water.
- Back filling on top of the pipe is from (300-900mm). Assembly of Pipes SAES-S-070 & SAES-L-610
- Pipes shall not move after joint is completed till it cures.
- Cure time of joints is depends on weather from (10-150 Minutes).
- If required external heating shall be given for (120 Min – at 90 – 120°C).
- All material used for lamination shall be from manufacturer.
- Follow the manufacturer instructions for lamination.
- All the solvents shall be mixed as per manufacturer.
- Pipe joints shall be made in trenches.
Any Change Or Addition please inform pg. 17 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
- Flat Face flanges shall be used in piping system.
- Pipes can be backfilled partially with joints exposed.
- Handle the pipes with care during assembly & Installation. Inspection of Joints SAES-S-070 & SAES-L-610
- As per ASTM D2563.
- Visual inspection of joints for any defects.
- Heating Time & Socking Time.
- Barcol Hardness Test (Min- 30 value).
- Repair of Joints & Damages (As per Manufacturer).
- Distance B/W 2 joints not less than 0.6 Mtr (2ft).
- Visual Inspection Acceptance Criteria refer SAES-L-650 Appendix A o Crack,Void,Crazing,DrySpot,Burn,Chip,PinHole,ImpactMark Hydro Testing SAES-L-610
- Gauges, Manifold, Test Package, Check list, Re-instatement as same as Metallic Piping.
- Water: Potable water, Drinking Water or Sea water can be used for hydro test.
- Hydro test for 4 Hr. when joints as exposed for visual leakage.
- Hydro test for 24 Hr. when joints are backfilled and recorded on thermal recorder. Bolt tightening procedures and maximum torque for bolting on nonmetallic flanges shall be in accordance with ASTM D4024. NOTE: All the activities will be same as above ground piping except few.
Any Change Or Addition please inform pg. 18 imad8asim@gmail.com +966540406799
Prepared By Mohammed Imaduddin Asim Rev: 2
Welding General Notes:
Notes
1: Welder Qualify for 2G + 5G is qualified for all positions.
2: Welder Qualify for 6G is qualified for all positions.
3: Position & Process of welder for which he is qualified.
4: Welder qualify for 1⁄2” thickness is qualified for 2times the thickness Eg: 12.7mm thickness = 25.4mm thickness. 5: Welder qualify for 1” thickness is qualified for unlimited thickness Eg: 25.4mm thickness = Unlimited thickness. 6: JCC card: Job Clearance Card (Have to Check).
i) P numbers ii) F numbers iii) Thickness iv) Process v) Position vi) Uphill/Downhill vii) Backing.
i) P-numbers = Refer to Base material.
ii) F-numbers = Refer to Filler material.
iii) Thickness = Refer to thickness of pipe.
iv) Process = GTAW (Gas Tungsten Arc Weld) / SMAW (Submerged Arc Weld) v) Position = 1G/2G/5G/6G.
vi) = Uphill / Downhill.
vii) Backing = Using any shield during welding from back side of the weldment.
All information shared from this page is just for education purposes.